A
bill of material can be created to support the preventative maintenance
work.
In
the Route module, the bill of material is associated with the route that
is specified in the preventative maintenance record.
Maintenance
type work orders, which include the route and material list, are used to
service work centers.
The
work orders may be created manually or automatically by the Machine
module.
The
materials requirements planning (MRP) process includes the maintenance
type work orders so that components required for the service work are
available for the scheduled maintenance.
The
Schedule module includes the maintenance type work orders in its
planning so that specific times in the production plan are reserved for
scheduled maintenance.
The
maintenance type work orders collect labor, material and overhead costs
so that the real cost of the service work is known and accounted for.
A
Group Definition function allows a group of work centers to be
created that need to share some limited common resource, such as labor
or molds.
The
Group Definition function provides a second constraint and is
used by the scheduler to report when the capacity of the group is
exceeded.
A
schedule of the dates and times the factory is closed can be created.
These
closed dates and times are observed by the scheduler.
A
Change Work Centers function provides a shortcut to making mass
changes for a range of work centers. It can quickly change: