The primary
Manufacturing links are through
the SAGE Pro Inventory Control module. Manufacturing's internal inventory
file is disabled and replaced by the inventory information in
SAGE Pro when the two systems are integrated. While maintenance of
the inventory file is done through SAGE Pro, Manufacturing can be used to
create new item numbers and locations in the file in order to support
the rapid creation of bills of material.
The SAGE Pro inventory valuation
methods by item are supported.
Manufacturing uses the following method to
determine if an item is made or purchased:
-
An item is treated as a purchased
item when the Used In Purchase Order option is
checked.
-
An item is treated as a manufactured
item when the Used In Work Order option is checked.
-
An item is treated as both a
purchased item and a manufactured item when the Used In
Purchase Order and Work Order options are
checked.
Unit of measure established in
SAGE Pro are used in Manufacturing.
The decimal settings in inventory are
observed by Manufacturing.
Manufacturing
uses the following method to
determine if an item is stock or nonstock:
An item is treated as a stock item if
the Check On-hand and Update On-hand
options are checked.
An item is treated as a nonstock item
if the Check On-hand and Update On-hand
options are left unchecked.
The lot/serial number processes are
supported. Manufacturing extends the support to provided lot/serial number
traceability.
Warehouse and bin locations are
supported.
The On-hand Qty field is
updated as finished goods are posted or items returned to inventory.
The In-process Qty field is
updated with quantity of items being manufactured.
The Allocated Qty field is
updated with the quantity of items allocated to work orders.
The Class field is used as
the Product Class field in Manufacturing.
The Product Line field is
used as the Code field in Manufacturing.
The MRP (Material Requirements Planning)
and Plan processes in Manufacturing included the item reorder, reorder
quantity, and vendor information.
The In-transit quantities
are excluded from MRP and Plan processes in Manufacturing.
The Manufacturing material planning Cushion
option may be used to partially offset the absence of item lead
times in SAGE Pro.
Procedures for controlling
Manufacturing transactions affecting inventory should be used during the periods in
which there is an SAGE Pro freeze on inventory. Manufacturing does not
stop transactions from occurring during these periods.
|